IRVING ISD 2009 RENOVATIONS & ADDITIONS

1501 N. BRITAIN, Irving, TX 75061, Irving, TX, 75061
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB0802183
$4.1M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
9 months
Duration
Registered:Oct 20, 2009
Start:Jan 1, 2010
Target:Oct 1, 2010
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Addition of new cafeteria, renovation of existing cafeteria into classroom and faculty rooms, carpet, flooring a

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 20, 2009
Construction Start
January 1, 2010
Expected Completion
October 1, 2010