๐Project Closed๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
CLINIC FINISH-OUT
1018 EAST 5TH ST, Tyler, TX 75701, Tyler, TX, 75701
Completed100%
๐Project Metrics
TDLR #EABPRJB0802962$2.0M
Project Value
โ
Square Feet
โ
Cost/SqFt
6 months
Duration
Registered:Nov 7, 2009
Start:Nov 1, 2009
Target:May 1, 2010
๐
Project Closed
Project has been completed and closed
๐Scope of Work
FINISH OUT OF EXISTING SPACE
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 7, 2009
Construction Start
November 1, 2009
Expected Completion
May 1, 2010
๐Related Projects
๐คSame Owner
$2.3M total๐๏ธSame Design Firm
$7.2M totalProperty Owner
๐ค
ETMC HOSPITAL FOUNDATION
2 projects ยท $2.3M
BOB HAMPTON P O BOX 6400, TYLER, TX 75711
Design Firm
๐๏ธ
FITZPATRICK BUTLER ARCHITECTS
4 projects ยท $7.2M
STEVE FITZPATRICK 1510 SOUTH VINE AVENUE, TYLER, TX 75701