๐Project Closed๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
HILLCREST KITCHEN FINISH OUT
211 W. MALONE, San Antonio, TX 78214, San Antonio, TX, 78214
Completed100%
๐Project Metrics
TDLR #EABPRJB2807817$950K
Project Value
โ
Square Feet
โ
Cost/SqFt
4 months
Duration
Registered:Feb 13, 2012
Start:Apr 1, 2012
Target:Aug 1, 2012
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Finish out existing kitchen shell and convert existing kitchen to a platform.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 13, 2012
Construction Start
April 1, 2012
Expected Completion
August 1, 2012
๐Related Projects
๐คSame Owner
$54.9M totalProperty Owner
๐ค
SAN ANTONIO INDEPENDENT SCHOOL DISTRICT
4 projects ยท $54.9M
OSCAR PEREZ 141 LAVACA, SAN ANTONIO, TX 78210
Design Firm
๐๏ธ
NOONAN RITTIMANN ARCHITECTS LLC
4 projects ยท $30.0M
JOHN RITTIMANN 2002 N. ST. MARY'S, SAN ANTONIO, TX 78212