๐ŸProject Closed๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

LEWISVILLE HIGH SCHOOL AUDITORIUM

1098 W. MAIN STREET, Lewisville, TX 75067, Lewisville, TX, 75067
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB2815321
$7.0M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1y 3mo
Duration
Registered:Jun 25, 2012
Start:Oct 1, 2012
Target:Jan 1, 2014
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

New 1100 seat auditorium

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 25, 2012
Construction Start
October 1, 2012
Expected Completion
January 1, 2014