๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

NAVASOTA 2011 TCF DOWNTOWN SIDEWALK REV.

200 E. MCALPINE, Navasota, TX 77868, Navasota, TX, 77868
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB2817445
$160K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1y 8mo
Duration
Registered:Aug 2, 2012
Start:Sep 1, 2012
Target:Apr 30, 2014
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Demolition/removal and reconstruction of existing sidewalks, curb & gutter, an alley intersection with a street,

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 2, 2012
Construction Start
September 1, 2012
Expected Completion
April 30, 2014