๐Project Closed๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
LEVEL 1 PROCEDURE ROOM RENO
1333 MOURSUND ST, Houston, TX 77030, Houston, TX, 77030
Completed100%
๐Project Metrics
TDLR #EABPRJB3803269$76K
Project Value
โ
Square Feet
โ
Cost/SqFt
4 months
Duration
Registered:Nov 5, 2012
Start:Nov 1, 2012
Target:Mar 1, 2013
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Renovation of a Prep and Recovery area. Adding an additional prep station and renovating the nurse station/cont
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 5, 2012
Construction Start
November 1, 2012
Expected Completion
March 1, 2013
๐Related Projects
๐คSame Owner
$900K total๐๏ธSame Design Firm
$146K totalProperty Owner
๐ค
MEMORIAL HERMANN
4 projects ยท $900K
RICHARD MAPES 929 GESSNER, SUITE 2600, HOUSTON, TX 77024
Design Firm
๐๏ธ
JOSEPH R MAYTUM
2 projects ยท $146K