๐Project Closed๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
FINISAR FAB EXPANSION
600 MILLENNIUM DRIVE, Allen, TX 75013, Allen, TX, 75013
Completed100%
๐Project Metrics
TDLR #EABPRJB4803081$153K
Project Value
โ
Square Feet
โ
Cost/SqFt
2 months
Duration
Registered:Oct 23, 2013
Start:Oct 1, 2013
Target:Dec 1, 2013
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Renovate 2100 sf of existing manufacturing space for a new cleanroom manufacturing area.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 23, 2013
Construction Start
October 1, 2013
Expected Completion
December 1, 2013