SOUTHWEST HIGH SCHOOL SOCCER & TENNIS IM

11914 DRAGON LANE, San Antonio, TX 78252, San Antonio, TX, 78252
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB4805984
$2.0M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
6 months
Duration
Registered:Dec 12, 2013
Start:Feb 1, 2014
Target:Aug 1, 2014
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Construct new post-tensioned tennis courts, soccer field, support building with restrooms, concession, storage,

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 12, 2013
Construction Start
February 1, 2014
Expected Completion
August 1, 2014