🏁Project Closed🏗️ New Construction💵 This project is privately funded, on private land for private use.
GOLDTHWAITE WIND ENERGY O&M FACILITY
418 EAST FM 572, Goldthwaite, TX 76844, Goldthwaite, TX, 76844
Completed100%
📊Project Metrics
TDLR #EABPRJB4810131$1.2M
Project Value
—
Square Feet
—
Cost/SqFt
5 months
Duration
Registered:Feb 28, 2014
Start:Dec 1, 2013
Target:May 1, 2014
🏁
Project Closed
Project has been completed and closed
📋Scope of Work
A new office and maintenance building with parking, sidewalks and utilities
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
February 28, 2014
Construction Start
December 1, 2013
Expected Completion
May 1, 2014