POTH HIGH SCHOOL SCIENCE LAB ADDITION
506 N. DICKSON, Poth, TX 78147, Poth, TX, 78147
Completed100%
๐Project Metrics
TDLR #EABPRJB4811161$3.2M
Project Value
โ
Square Feet
โ
Cost/SqFt
7 months
Duration
Registered:Mar 17, 2014
Start:May 1, 2014
Target:Dec 1, 2014
๐
Project Closed
Project has been completed and closed
๐Scope of Work
new science lab building adjacent to Poth High School building.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 17, 2014
Construction Start
May 1, 2014
Expected Completion
December 1, 2014