Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB4815832
$14.5M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
3y 9mo
Duration
Registered:May 27, 2014
Start:Jun 1, 2010
Target:Feb 1, 2014
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Construction of the widening of a non-freeway facility consisting of grading, lime treatment, concrete pavement,

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 27, 2014
Construction Start
June 1, 2010
Expected Completion
February 1, 2014

Quick Actions

TDLR ID: EABPRJB4815832

Property Owner

๐Ÿ‘ค
CITY OF MONT BELVIEU, THE
RICARDO VILLAGRAND P.O. BOX 1048, MONT BELVIEU, TX 77580

Design Firm

๐Ÿ›๏ธ
R.G. MILLER ENGINEERS
4 projects ยท $15.2M