๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

EVERMAN ISD | HOMMEL ES RENOV & ADD

308 W ENON AVE, Everman, TX 76140, Everman, TX, 76140
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB5802816
$3.5M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
9 months
Duration
Registered:Oct 14, 2014
Start:Nov 1, 2014
Target:Aug 1, 2015
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Renovations and additions to Hommel Elementary School.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 14, 2014
Construction Start
November 1, 2014
Expected Completion
August 1, 2015