๐Project Closed๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
COCKRELL HILL ROAD MCIP 42301
FROM N OF MOLER ST TO DAVIS ST, Dallas, TX 75116, Dallas, TX, 75116
Completed100%
๐Project Metrics
TDLR #EABPRJB5809287$7.7M
Project Value
โ
Square Feet
โ
Cost/SqFt
4y 6mo
Duration
Registered:Feb 3, 2015
Start:Jan 1, 2016
Target:Jun 1, 2020
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Reconstruct pavement & widening, build roundabout at cockrell hill-Jefferson intersection, sidewalks/ramps, wate
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 3, 2015
Construction Start
January 1, 2016
Expected Completion
June 1, 2020