๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
CHALK HILL ROAD - SOUTH
BETWEEN DAVIS STREET AND I-30, Dallas, TX 75212, Dallas, TX, 75212
Completed100%
๐Project Metrics
TDLR #EABPRJB5820972$8.9M
Project Value
โ
Square Feet
โ
Cost/SqFt
1y 9mo
Duration
Registered:Jul 30, 2015
Start:Sep 1, 2015
Target:Jun 1, 2017
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Prepare plans to the complete reconstruction of Chalk Hill Road from Davis St. to I-30. Upgrading the road from
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 30, 2015
Construction Start
September 1, 2015
Expected Completion
June 1, 2017
๐Related Projects
Property Owner
๐ค
CITY OF DALLAS
4 projects ยท $3.6M
PUBLIC WORKS DEPARTMENT 320 E JEFFERSON, DALLAS, TX 75203
Design Firm
๐๏ธ
PARSONS BRINKERHOFF INC.
2 projects ยท $8.9M
AKAYU MEKONNEN 2777 N. STEMMONS FRWY., #1600, DALLAS, TX 75207