๐Project Closed๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
TIME VERSALIFT SOUTHWEST EXPANSION/ADDIT
1200 CENTRAL TEXAS PARKWAY, Waco, TX 76712, Waco, TX, 76712
Completed100%
๐Project Metrics
TDLR #EABPRJB5822323$2.8M
Project Value
โ
Square Feet
โ
Cost/SqFt
5 months
Duration
Registered:Aug 20, 2015
Start:Sep 1, 2015
Target:Feb 1, 2016
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Expansion of a pre-engineered metal building, addition of a pre-engineered metal building, electrical, plumbing,
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 20, 2015
Construction Start
September 1, 2015
Expected Completion
February 1, 2016
๐Related Projects
๐๏ธSame Design Firm
$3.6M totalProperty Owner
Design Firm
๐๏ธ
KISS ENGINEERING PLLC
3 projects ยท $3.6M
SAUL BALDERAS 445 RADLE ROAD, WACO, TX 76706