๐Project Closed๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
ANCILLARY SERVICES/SLEEP LAB EXPANSION
5323 HARRY HINES BLVD, Dallas, TX 75390, Dallas, TX, 75390
Completed100%
๐Project Metrics
TDLR #EABPRJB6805287$2.0M
Project Value
โ
Square Feet
โ
Cost/SqFt
11 months
Duration
Registered:Nov 23, 2015
Start:Feb 1, 2016
Target:Jan 1, 2017
๐
Project Closed
Project has been completed and closed
๐Scope of Work
renovation of POB 1/POB 2 into ancillary services and sleep lab areas. addition of a 2-hr fire rated corridor.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 23, 2015
Construction Start
February 1, 2016
Expected Completion
January 1, 2017
๐Related Projects
๐คSame Owner
$2.9M totalProperty Owner
Design Firm
๐๏ธ
VAI ARCHITECTS
4 projects ยท $6.8M
JEFF SIMCIK 16000 NORTH DALLAS PARKWAY, DALLAS, TX 75248