๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

D.A. HULCY MIDDLE SCHOOL

9339 SOUTH POLK STREET, Dallas, TX 75232, Dallas, TX, 75232
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB6808746
$2.2M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
9 months
Duration
Registered:Jan 27, 2016
Start:Jun 1, 2016
Target:Mar 1, 2017
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Renovation of existing classroom/ common space, exteriorflatwork replacment, and finish upgrades.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 27, 2016
Construction Start
June 1, 2016
Expected Completion
March 1, 2017