๐ŸProject Closed๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project is privately funded, on private land for private use.

DBU BURG CENTER ADDITION

3000 MOUNTAIN CREEK PKWY, Dallas, TX 75211, Dallas, TX, 75211
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB6809861
$550K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
6 months
Duration
Registered:Feb 10, 2016
Start:Feb 1, 2016
Target:Aug 1, 2016
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

For and existing 3 story campus basketball stadium/fitness center, only the lowest story is being altered to con

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 10, 2016
Construction Start
February 1, 2016
Expected Completion
August 1, 2016