STERLING FLY JUNIOR HIGH SCHOOL ADDS

715 W. CROCKETT, Crystal City, TX 78839, Crystal City, TX, 78839
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB6814472
$1.0M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1y 2mo
Duration
Registered:Apr 15, 2016
Start:Jun 1, 2016
Target:Aug 1, 2017
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Site package including utilities

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 15, 2016
Construction Start
June 1, 2016
Expected Completion
August 1, 2017