๐Project Closed๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
TESLA MOTORS ELECTRIC CAR CHARGING STA
2645 S. HWY 37, I-37, EXIT 72, Three Rivers, TX 78071, Three Rivers, TX, 78071
Completed100%
๐Project Metrics
TDLR #EABPRJB6817301$105K
Project Value
โ
Square Feet
โ
Cost/SqFt
1 months
Duration
Registered:May 25, 2016
Start:Jul 1, 2016
Target:Aug 1, 2016
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Install 8 Tesla Motors electric car charging stations; 4SuperCharger equipment cabinets; switchgear; transforme
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 25, 2016
Construction Start
July 1, 2016
Expected Completion
August 1, 2016
๐Related Projects
๐คSame Owner
$225K totalProperty Owner
๐ค
LOVE'S TRAVEL SHOPS
2 projects ยท $225K
KEVIN MCCARTHY 2645 S. HWY 37 ACCESS, THREE RIVERS, TX 78071
Design Firm
๐๏ธ
BLACK AND VEATCH
4 projects ยท $465K
NOEL HERRERA 10950 GRANDVIEW ST., BLDG 34, OVERLAND PARK, KS 66210