๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

US 90A

FROM LANE DRIVE TO FM 3155, Richmond, TX 77469, Richmond, TX, 77469
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB7801023
$59K
Project Value
1,000
Square Feet
$59/sqft
Cost/SqFt
2y 2mo
Duration
Registered:Sep 19, 2016
Start:Jan 6, 2025
Target:Mar 9, 2027
Remaining:443 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Construction of railroad overpass with sidewalk and ADAramps

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 19, 2016
Construction Start
January 6, 2025
Expected Completion
March 9, 2027