๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

TFCU NEW DRIVE-THRU ATM

1226 GOLDEN KEY CIRCLE, El Paso, TX 79925, El Paso, TX, 79925
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB8801702
$200K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
3 months
Duration
Registered:Sep 28, 2017
Start:Nov 1, 2017
Target:Feb 1, 2018
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

NEW DRIVE THRU ATM INCLUDING GRADING AND ASPHALT PARKING. 27,255 SQ. FT.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 28, 2017
Construction Start
November 1, 2017
Expected Completion
February 1, 2018