๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

207 KING ROAD PHASE 2

207 KING ROAD, Hackberry, TX 75034, Hackberry, TX, 75034
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB8803392
$450K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
7 months
Duration
Registered:Oct 23, 2017
Start:Nov 1, 2017
Target:Jun 1, 2018
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

New Warehouse building

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 23, 2017
Construction Start
November 1, 2017
Expected Completion
June 1, 2018