Inspection Complete๐ง Additions to Existing Building๐ต This project is privately funded, on private land for private use.
FIRST BAPTIST CHURCH BUFFALO GAP
1002 LITEL STREET, Buffalo Gap, TX 79508, Buffalo Gap, TX, 79508
Final Inspection85%
๐Project Metrics
TDLR #EABPRJB8814711$400K
Project Value
โ
Square Feet
โ
Cost/SqFt
1y 5mo
Duration
Registered:Apr 13, 2018
Start:May 1, 2018
Target:Sep 30, 2019
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
2,550 sqft children's addition.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 13, 2018
Construction Start
May 1, 2018
Expected Completion
September 30, 2019
๐Related Projects
๐๏ธSame Design Firm
$7.8M totalProperty Owner
๐ค
FIRST BAPTIST CHURCH BUFFALO GAP
CHUCK GILLILAND 1002 LITEL STREET, BUFFALO GAP, TX 79508
Design Firm
๐๏ธ
HALO ARCHITECTS INC.
4 projects ยท $7.8M
LUKE QUEBE 5109 82ND STREET, SUITE 7, LUBBOCK, TX 79424