โ
Inspection Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
SL 335 SEGMENT B2 PHASE 2
INTERSECTION OF IH40 & SL 335, Amarillo, TX 79106, Amarillo, TX, 79106
Final Inspection85%
๐Project Metrics
TDLR #EABPRJB8817555$46.3M
Project Value
โ
Square Feet
โ
Cost/SqFt
3 years
Duration
Registered:May 21, 2018
Start:Sep 1, 2019
Target:Aug 1, 2022
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
B-2 Phase II: Reconstruct IH 40 2nd Level Mainlane Bridge at SL 335 and Frontage Road Box
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 21, 2018
Construction Start
September 1, 2019
Expected Completion
August 1, 2022
๐Related Projects
๐คSame Owner
$115.7M totalProperty Owner
๐ค
TXDOT DISTRICT: AMARILLO
4 projects ยท $115.7M
RANDY HOCHSTEIN P.O. BOX 7368, AMARILLO, TX 79114
Design Firm
๐๏ธ
HUITT-ZOLLARS
4 projects ยท $1.8M