๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
IH10
BEXAR/KENDALL CL TO FAIR OAKS, Boerne, TX 78006, Boerne, TX, 78006
Completed100%
๐Project Metrics
TDLR #EABPRJB8818997$760K
Project Value
โ
Square Feet
โ
Cost/SqFt
2y 6mo
Duration
Registered:Jun 8, 2018
Start:Sep 1, 2018
Target:Mar 1, 2021
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Construct Grade Separations at Balcones Creek Road, Reconfigure Ramps and Widen Frontage Roads to Convert to One
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
June 8, 2018
Construction Start
September 1, 2018
Expected Completion
March 1, 2021
๐Related Projects
๐คSame Owner
$639K totalProperty Owner
๐ค
TXDOT DISTRICT : SAN ANTONIO
4 projects ยท $639K
MARSHALL HEAP II, P.E. 4615 N.W. LOOP 410, SAN ANTONIO, TX 78229
Design Firm
๐๏ธ
HALFF
4 projects ยท $1.1M
EDWARD HEROLT, P.E. 300 E. SONTERRA BLVD., STE 230, SAN ANTONIO, TX 78208