๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
FM 2478 (N CUSTER RD)
FROM US 380 TO N OF FM 1461, Prosper, TX 75071, Prosper, TX, 75071
Completed100%
๐Project Metrics
TDLR #EABPRJB8822610$30.1M
Project Value
โ
Square Feet
โ
Cost/SqFt
2y 2mo
Duration
Registered:Jul 30, 2018
Start:Sep 1, 2020
Target:Nov 1, 2022
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Widen two lane rural highway to four lane divided: Six lane ultimate, realign intersection of FM 1461
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 30, 2018
Construction Start
September 1, 2020
Expected Completion
November 1, 2022
๐Related Projects
Property Owner
๐ค
TXDOT DISTRICT: DALLAS
4 projects ยท $440.3M
_ 4777 E HIGHWAY 80, MESQUITE, TEXAS 75150
Design Firm
๐๏ธ
KENNEDY CONSULTING
TRAVIS PHEMISTER, P.E. 1871 HARROUN AVENUE, SUITE 101, MCKINNEY, TX 75069