TULIA ISD 2017 BOND ISSUE PROJECTS
702 NW 8TH STREET, Tulia, TX 79088, Tulia, TX, 79088
Completed100%
๐Project Metrics
TDLR #EABPRJB9800534$15.0M
Project Value
โ
Square Feet
โ
Cost/SqFt
1y 9mo
Duration
Registered:Sep 10, 2018
Start:Nov 1, 2018
Target:Aug 1, 2020
๐
Project Closed
Project has been completed and closed
๐Scope of Work
ADDITIONS TO ELEMENTARY AND HIGH SCHOOL CAMPUS
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
September 10, 2018
Construction Start
November 1, 2018
Expected Completion
August 1, 2020
๐Related Projects
๐๏ธSame Design Firm
$20.1M totalProperty Owner
Design Firm
๐๏ธ
SHIVER MEGERT & ASSOCIATES LLP.
4 projects ยท $20.1M
RICHARD CONSTANCIO JR 102 E. NINTH AVE. SUITE 200, AMARILLO, TX 79101