โ
Inspection Complete๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
COLOGIX DAL3 (EQUINIX DATA CENTER)
1950 N STEMMONS FRWY, Dallas, TX 75207, Dallas, TX, 75207
Final Inspection85%
๐Project Metrics
TDLR #EABPRJB9804282$25.0M
Project Value
โ
Square Feet
โ
Cost/SqFt
6 months
Duration
Registered:Nov 1, 2018
Start:Jan 1, 2019
Target:Jul 1, 2019
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
Renovation; partial second floor for data hall, mezzanine for mechanical and electrical equipment, generator equ
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 1, 2018
Construction Start
January 1, 2019
Expected Completion
July 1, 2019