๐ŸProject Closed๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

RBPE-GROUP B-RED LINE NORTH

1300 E. PRESIDENT BUSH TURNPIK, Richardson, TX 75082, Richardson, TX, 75082
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB9804526
$962K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
4 months
Duration
Registered:Nov 5, 2018
Start:May 1, 2020
Target:Sep 1, 2020
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Extend existing transit boarding platform to accommodatean additional LRV. Project also includes relocation of

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 5, 2018
Construction Start
May 1, 2020
Expected Completion
September 1, 2020