๐Project Closed๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
MONTICELLO CT. - HILLJE TO LYRIC
MONTICELLO CT., San Antonio, TX 78223, San Antonio, TX, 78223
Completed100%
๐Project Metrics
TDLR #EABPRJB9806120$77K
Project Value
โ
Square Feet
โ
Cost/SqFt
2 months
Duration
Registered:Nov 29, 2018
Start:Oct 1, 2018
Target:Dec 1, 2018
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Curb, Sidewalk and Driveway Construction
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 29, 2018
Construction Start
October 1, 2018
Expected Completion
December 1, 2018
๐Related Projects
๐คSame Owner
$1.4M totalProperty Owner
๐ค
CITY OF SAN ANTONIO
4 projects ยท $1.4M
CARMEN VARELA-RIVAS 114 W. COMMERCE ST., SAN ANTONIO, TX 78205
Design Firm
๐๏ธ
LOCKWOOD ANDREWS & NEWNAM INC.
4 projects ยท $398K
10101 REUNION PLACE, SUITE 200, SAN ANTONIO, TX 78216