๐Project Closed๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Cudd Energy - Truck Wash
1434 CR 1422, Pleasanton, TX 78604, Pleasanton, TX, 78604
Completed100%
๐Project Metrics
TDLR #TABS2019009067$350K
Project Value
800
Square Feet
$438/sqft
Cost/SqFt
3 months
Duration
Registered:Apr 10, 2019
Start:May 10, 2019
Target:Jul 31, 2019
๐
Project Closed
Project has been completed and closed
๐Scope of Work
The project scope consists in a new PEMB that will house 2 wash bays, Truck docking areas and storage areas.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 10, 2019
Construction Start
May 10, 2019
Expected Completion
July 31, 2019