๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
S Church St
Fr E Main St to SS 264, Quinlan, TX 75474, Quinlan, TX, 75474
Completed100%
๐Project Metrics
TDLR #TABS2019013135$153K
Project Value
11,088
Square Feet
$14/sqft
Cost/SqFt
8 months
Duration
Registered:Jun 4, 2019
Start:Dec 15, 2019
Target:Aug 15, 2020
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Construct 5' wide reinforced concrete sidewalk on South Church Street from East Main Street to DC Cannon Elementary School on SS 264.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
June 4, 2019
Construction Start
December 15, 2019
Expected Completion
August 15, 2020