🏁Project Closed🏗️ New Construction💵 This project involves public funds, public land, or is a Federally funded roadway project.

66-inch Water Line Interconnection Along W. Hardy Rd From BW8 to Greens Rd.

West Hardy Rd Between BW-8 to Greens Rd., Houston, TX 77060, Houston, TX, 77060
Completed100%

📊Project Metrics

TDLR #TABS2019014088
$225K
Project Value
22,750
Square Feet
$10/sqft
Cost/SqFt
1y 2mo
Duration
Registered:Jun 14, 2019
Start:Nov 2, 2020
Target:Dec 23, 2021
🏁

Project Closed

Project has been completed and closed

📋Scope of Work

Install sidewalk along the northbound lanes of West Hardy Rd. from Beltway 8 to Greens Rd. Also included in this project are installation of a 66" WL and redesign of the northbound lanes.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
June 14, 2019
Construction Start
November 2, 2020
Expected Completion
December 23, 2021

Quick Actions

TDLR ID: TABS2019014088

Property Owner

👤
City of Houston Public Works - Kevin Tran
611 Walker 15th floor, Hoston, Texas 77002

Design Firm

🏛️
Aurora Technical Services LLC
2121 Sage Road Suite 150, Houston, Texas 77056

Registered Accessibility Specialist

📋
DOUGLAS W,DARR
RAS #3
12542 RIVA RIDGE LN, HOUSTON, TX 77071