๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Spring Canyon Elementary

Buckston Dr., Canyon, TX 79015, Canyon, TX, 79015
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2019015512
$18.0M
Project Value
78,000
Square Feet
$231/sqft
Cost/SqFt
1y 11mo
Duration
Registered:Jul 3, 2019
Start:Sep 1, 2019
Target:Aug 1, 2021
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

NEW CONSTRUCTION OF A 78,000 SF K-4 ELEMENTARY SCHOOL.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 3, 2019
Construction Start
September 1, 2019
Expected Completion
August 1, 2021