๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Southlake Restroom Remodel - 2nd and 3rd Floors

1400 Main St, Southlake, TX 76092, Southlake, TX, 76092
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2019017069
$75K
Project Value
1,500
Square Feet
$50/sqft
Cost/SqFt
2 months
Duration
Registered:Jul 26, 2019
Start:Jul 29, 2019
Target:Sep 15, 2019
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Replacement of all wall & floor finishes and faucets. Update of RR entrances to meet ADA

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 26, 2019
Construction Start
July 29, 2019
Expected Completion
September 15, 2019