Garland Road Sidewalk at the Arboretum Frontage

8525 Garland Road, Dallas, TX 75218, Dallas, TX, 75218
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2019019535
$315K
Project Value
15,500
Square Feet
$20/sqft
Cost/SqFt
1y 3mo
Duration
Registered:Aug 29, 2019
Start:Jan 1, 2019
Target:Apr 1, 2020
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Sidewalk along Garland Road for the frontage of the Dallas Arboretum, with barrier free curb ramps. Accessible ramp at the north property line and gate access at the main entry.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 29, 2019
Construction Start
January 1, 2019
Expected Completion
April 1, 2020