๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

VALLEY CREEK CHURCH GAINESVILLE CAMPUS

201 CULBERSON STREET, Gainesville, TX 75067, Gainesville, TX, 75067
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020002193
$2.0M
Project Value
21,977
Square Feet
$91/sqft
Cost/SqFt
5 months
Duration
Registered:Oct 2, 2019
Start:Nov 1, 2019
Target:Mar 27, 2020
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Interior and exterior renovation of existing property for use as a Church Campus to include Worship Center, Meeting Rooms and Children's Areas. Parking lot will be added. Claiming areas as "places used primarily for religious purposes."

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 2, 2019
Construction Start
November 1, 2019
Expected Completion
March 27, 2020