๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Eagle Pass Renal Care Facility
3414 Amy Street, Eagle Pass, TX 78805, Eagle Pass, TX, 78805
Construction50%
๐Project Metrics
TDLR #TABS2020002645$1.2M
Project Value
3,900
Square Feet
$308/sqft
Cost/SqFt
2y 2mo
Duration
Registered:Oct 8, 2019
Start:Dec 2, 2019
Target:Feb 1, 2022
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
new ground up medical office
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 8, 2019
Construction Start
December 2, 2019
Expected Completion
February 1, 2022
๐Related Projects
๐๏ธSame Design Firm
$2.0M totalProperty Owner
๐ค
RAPA Eagle Pass Holdings, LLC
16620 US HWY 281, suite 300, San Antonio, Texas 78232
Design Firm
๐๏ธ
kyle tostenson architects
3 projects ยท $2.0M