๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Oscar Perez Park Site Improvements

8601 Timber Path, San Antonio, TX 78250, San Antonio, TX, 78250
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020005746
$275K
Project Value
740,520
Square Feet
$0/sqft
Cost/SqFt
1y 8mo
Duration
Registered:Nov 19, 2019
Start:Jan 1, 2020
Target:Sep 1, 2021
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Expansion of parking, limited lighting, limited planting, relocation of softball field

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 19, 2019
Construction Start
January 1, 2020
Expected Completion
September 1, 2021