Laney Directional Drilling Headquarters Build Out

1100 Alegacy Place, Waller, TX 77484, Waller, TX, 77484
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020006177
$360K
Project Value
23,700
Square Feet
$15/sqft
Cost/SqFt
3 months
Duration
Registered:Nov 25, 2019
Start:Nov 25, 2019
Target:Feb 25, 2020
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Interior Build Out

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 25, 2019
Construction Start
November 25, 2019
Expected Completion
February 25, 2020