โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Dallas County West Government Center

702 East Jefferson Boulevard, Dallas, TX 75203, Dallas, TX, 75203
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020007639
$16.0M
Project Value
43,500
Square Feet
$368/sqft
Cost/SqFt
1y 8mo
Duration
Registered:Dec 17, 2019
Start:Jan 2, 2020
Target:Aug 20, 2021
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

New Governmental Building; Two Floors

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 17, 2019
Construction Start
January 2, 2020
Expected Completion
August 20, 2021