๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

FM 1472 - Killam Industrial Blvd Turn Lanes

FM 1472 and Killam Industrial Blvd, Laredo, TX 78045, Laredo, TX, 78045
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020016407
$1.2M
Project Value
9,162
Square Feet
$131/sqft
Cost/SqFt
2y 4mo
Duration
Registered:Apr 28, 2020
Start:Sep 1, 2020
Target:Jan 1, 2023
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Construction of widening a principal arterial facility, consisting of grading, pavement, signing, pavement markings, and traffic signal adjustments.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 28, 2020
Construction Start
September 1, 2020
Expected Completion
January 1, 2023

๐Ÿ“Location & Views

Open in MapsGet Directions|27.69836, -99.25236