๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

North Fork Dialysis

4801 N. Ware Rd., Mcallen, TX 78504, Mcallen, TX, 78504
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020017201
$1.2M
Project Value
10,375
Square Feet
$116/sqft
Cost/SqFt
6 months
Duration
Registered:May 12, 2020
Start:Jun 15, 2020
Target:Dec 15, 2020
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

New ground up building with interior build-out for dialysis center.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 12, 2020
Construction Start
June 15, 2020
Expected Completion
December 15, 2020