3rd Street Reconstruction
Shaw to Davis, Taylor, TX 76574, Taylor, TX, 76574
Completed100%
๐Project Metrics
TDLR #TABS2020017202$1.4M
Project Value
1,321
Square Feet
$1.03K/sqft
Cost/SqFt
7 months
Duration
Registered:May 12, 2020
Start:Jun 29, 2020
Target:Jan 15, 2021
๐
Project Closed
Project has been completed and closed
๐Scope of Work
0.25 miles of local street reconstruction consisting of asphalt pavement, base material, grading, sidewalks, culverts, erosion control, driveways, signing, pavement markings, and utilities
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 12, 2020
Construction Start
June 29, 2020
Expected Completion
January 15, 2021
๐Related Projects
๐คSame Owner
$8.4M total๐Nearby Projects
Within 1 kmProperty Owner
๐ค
City of Taylor
Contact: Jim Gray
4 projects ยท $8.4M
400 Porter Street, Taylor, Texas 76574
Design Firm
๐๏ธ
HDR Engineering
4 projects ยท $18.5M
710 Hesters Crossing, Suite 150, Round Rock, Texas 78681
Registered Accessibility Specialist
๐
ARTURO ALEXANDER OCHOA,PINERO
RAS #1551
10800 LAKELINE BLVD APT 13207, AUSTIN, TX 78717