Inspection Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Robinson Street Reconstruction
3rd St to Frank St, Taylor, TX 76574, Taylor, TX, 76574
Final Inspection85%
๐Project Metrics
TDLR #TABS2020017206$1.5M
Project Value
1,742
Square Feet
$856/sqft
Cost/SqFt
1y 1mo
Duration
Registered:May 12, 2020
Start:Jun 29, 2020
Target:Jul 30, 2021
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
0.33 miles of local street reconstruction consisting of asphalt pavement, base material, grading, sidewalks, erosion control, driveways, signing, pavement markings, and utilities
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 12, 2020
Construction Start
June 29, 2020
Expected Completion
July 30, 2021
๐Related Projects
๐คSame Owner
$8.5M totalProperty Owner
๐ค
City of Taylor
Contact: Jim Gray
4 projects ยท $8.5M
400 Porter Street, Taylor, Texas 76574
Design Firm
๐๏ธ
HDR Engineering
4 projects ยท $18.5M
710 Hesters Crossing Suite 150, Round Rock, Texas 78681