๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

University of Texas at Tyler Sidewalk Improvements Phase 3A

3900 University Boulevard, Tyler, TX 75799, Tyler, TX, 75799
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020018108
$1.5M
Project Value
165,528
Square Feet
$9/sqft
Cost/SqFt
3 months
Duration
Registered:May 29, 2020
Start:Aug 1, 2020
Target:Oct 31, 2020
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

New parking lot and sidewalk to serve the University

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 29, 2020
Construction Start
August 1, 2020
Expected Completion
October 31, 2020