โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

19-088 Goose Creek CISD - Stuart Career Tech High School Phase IV

300 YMCA Dr., Baytown, TX 77521, Baytown, TX, 77521
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020021233
$13.2M
Project Value
51,400
Square Feet
$257/sqft
Cost/SqFt
10 months
Duration
Registered:Jul 28, 2020
Start:Oct 5, 2020
Target:Jul 30, 2021
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

SCOPE OF WORK CONSISTS OF, BUT IS NOT LIMITED TO, NEW CLASSROOMS, LABS, RESTROOMS, OFFICES AND ASSOCIATED ANCILLARY SPACES, PARKING, SITE WORK, HEATING, AIR CONDITIONING, ELECTRICAL, PLUMBING, AND TELECOMMUNICATIONS.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 28, 2020
Construction Start
October 5, 2020
Expected Completion
July 30, 2021