D1 Pedestrian Mobility & Streets - Errol St.
Errol St. from Sunset to Chulie, San Antonio, TX 78216, San Antonio, TX, 78216
Completed100%
๐Project Metrics
TDLR #TABS2021000434$55K
Project Value
5,580
Square Feet
$10/sqft
Cost/SqFt
2 months
Duration
Registered:Sep 9, 2020
Start:Nov 1, 2020
Target:Jan 4, 2021
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Public sidewalk construction
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
September 9, 2020
Construction Start
November 1, 2020
Expected Completion
January 4, 2021
๐Related Projects
๐คSame Owner
$440K totalProperty Owner
๐ค
The City of San Antonio
Contact: Eric Salazar
4 projects ยท $440K
PO Box 839966, San Antonio, Texas 78283
Design Firm
๐๏ธ
MW Cude Engineers, LLC
4 projects ยท $7.4M
4122 Pond Hill Road, Ste. 101, San Antonio, Texas 78231