๐ŸProject Closed๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Midway ISD CTE Additions and Renovations at Midway High School

8200 Mars Drive, Waco, TX 76712, Waco, TX, 76712
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2021001167
$23.4M
Project Value
64,318
Square Feet
$364/sqft
Cost/SqFt
1y 8mo
Duration
Registered:Sep 22, 2020
Start:Nov 1, 2020
Target:Jul 5, 2022
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

CTE addition and renovations Midway High School

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 22, 2020
Construction Start
November 1, 2020
Expected Completion
July 5, 2022